Tallai v Ellair: no EOT claim, so subcontract LDs ran to the cap
The NSW Supreme Court held a subcontractor that never claimed an extension of time was bound by its "Estimated" completion dates, despite late site access. Liquidated damages ran to a cap measured portion by portion.